Application of Critical Chain Project Management (CCPM) for infrastructure project: A case study
Milan R. Sheta
M.E. C.E.M, S.N.P.I.T & R.C , IN
Neetu B. Yadav
M.E. C.E.M, S.N.P.I.T & R.C , IN
Keywords: Critical Chain; Primavera scheduler; Project Management; Scheduling; Software.
Abstract
Critical Chain Project Management is a scheduling tool which is used for planning and managing projects based on the resources that required to execute project tasks within predefined time and budget. In this research work primavera P6 based step by step process of scheduling which helps in applying CCPM infrastructure projects was identified. The detail process of scheduling starts with identification of tasks, resources, activities, calculation of labour productivity, labour assignment and at last assign duration for each activity based on which resource availability is checked and finally authors were able to prepared final CCPM schedule for particular activities.